Service Impact to AM2, DFW3, FR4, FRA2, LON3, SJC1, SJC2 Data Center.
Netskope experienced a critical incident on September 30, 2025 affecting AM2 — Amsterdam, Netherlands and DFW3 — Dallas, United States and 1 more component, lasting 21h 7m. The incident has been resolved; the full update timeline is below.
Affected components
Update timeline
- investigating Sep 30, 2025, 03:14 PM UTC
We are currently investigating this issue.
- resolved Sep 30, 2025, 03:14 PM UTC
We are investigating a service impacting incident at the AM2, DFW3, FR4, FRA2, LON3, SJC1, SJC2 datacenter(s) for the following service(s) Event Logging. Full details can be found on the support portal.
- resolved Sep 30, 2025, 03:36 PM UTC
Netskope has identified a potential root cause and is implementing a mitigation strategy to isolate the issue.
- resolved Sep 30, 2025, 03:54 PM UTC
Netskope has confirmed that the mitigation strategy implemented was successful in isolating the issue and preventing further impact on SkopeIT application events and alerts. Root cause investigation remains underway. Additional details can be found in the support portal.
- monitoring Sep 30, 2025, 04:39 PM UTC
The issue has been mitigated, we are continuing to monitor the results.
- resolved Sep 30, 2025, 04:40 PM UTC
Currently the platform is processing the delayed SkopeIT application events and alerts within all impacted MPs. Current estimated completion time has been provided within the support portal article. The incident will be marked resolved once all event lag has been completely processed.
- resolved Oct 01, 2025, 12:26 AM UTC
The majority of MP’s have had their application event and alert lag drained. SJC1, SJC2 and DFW3 remain in a processing status with estimate of roughly 1 to 2 hours remaining.
- resolved Oct 01, 2025, 12:21 PM UTC
The incident has been resolved