Hyland experienced a minor incident on May 15, 2026 affecting Boyers, USA (PIT), lasting 37m. The incident has been resolved; the full update timeline is below.

Started
May 15, 2026, 06:49 PM UTC
Resolved
May 15, 2026, 07:27 PM UTC
Duration
37m
Detected by Pingoru
May 15, 2026, 06:49 PM UTC

Affected components

Boyers, USA (PIT)

Update timeline

  1. investigating May 15, 2026, 06:49 PM UTC

    Hyland is aware of increased error rates in the PIT data center. Hyland is engaged and investigating this issue with the highest priority. Additional details will be provided as they become available.

  2. resolved May 15, 2026, 07:27 PM UTC

    Hyland has identified and resolved the issue. If you continue to have any issues please contact your first line of Hyland support.