Pulsant experienced a notice incident on July 6, 2025 affecting LN-1 - South London, lasting 3h 31m. The incident has been resolved; the full update timeline is below.
Affected components
LN-1 - South London
Update timeline
- monitoring Jul 06, 2025, 12:22 PM UTC
Currently the access road to Croydon Data centre LN-1 is closed due a skip plant fire just down the road. No data centre services are affected. Public access is still available on foot via the green field to the side of the data centre, but main on road parking is very congested.
- resolved Jul 06, 2025, 03:53 PM UTC
This incident has been resolved.