EnxadaHost incident

Indisponibilidade do node ENX-CIRION-51

Critical Resolved View vendor source →

EnxadaHost experienced a critical incident on September 27, 2025 affecting ENX-CIRION-51, lasting 6d 20h. The incident has been resolved; the full update timeline is below.

Started
Sep 27, 2025, 09:37 PM UTC
Resolved
Oct 04, 2025, 05:44 PM UTC
Duration
6d 20h
Detected by Pingoru
Sep 27, 2025, 09:37 PM UTC

Affected components

ENX-CIRION-51

Update timeline

  1. identified Sep 27, 2025, 09:37 PM UTC

    Estamos cientes do problema no ENX-CIRION-51 e nossa equipe já está no Datacenter para investigar a causa. Pedimos desculpas pelo transtorno e forneceremos novas atualizações assim que possível. Agradecemos pela compreensão.

  2. resolved Oct 04, 2025, 05:44 PM UTC

    This incident has been resolved.