Switchio incident

Unplanned Outage of DINIT Processing Centre

Critical Resolved View vendor source →

Switchio experienced a critical incident on August 31, 2026 affecting DINIT Processing Centre, lasting 27m. The incident has been resolved; the full update timeline is below.

Started
Aug 31, 2026, 08:02 PM UTC
Resolved
Aug 31, 2026, 08:30 PM UTC
Duration
27m
Detected by Pingoru
Aug 31, 2026, 08:02 PM UTC

Affected components

DINIT Processing Centre

Update timeline

  1. investigating Aug 31, 2026, 08:02 PM UTC

    We are currently experiencing an unplanned service outage in production that might affect you. Our technical teams are actively working to resolve the issue. Internal ticket MONET+ TSGCTCNAG-962564

  2. investigating Aug 31, 2026, 08:22 PM UTC

    Problem detected at the issuer/processor side. They have been contacted. No reply so far.

  3. monitoring Aug 31, 2026, 08:30 PM UTC

    We are pleased to inform you that the system outage previously communicated has been resolved. We will monitor it.

  4. resolved Aug 31, 2026, 08:30 PM UTC

    We are pleased to confirm that the system outage was fully mitigated.

  5. postmortem Aug 31, 2026, 09:13 PM UTC

    Problem detected at the issuer/processor side. They have been contacted. No reply so far. The outage was from 21:58 to 22:53.