Switchio experienced a critical incident on July 7, 2026 affecting DINIT Processing Centre, lasting 22m. The incident has been resolved; the full update timeline is below.

Started
Jul 07, 2026, 08:27 PM UTC
Resolved
Jul 07, 2026, 08:50 PM UTC
Duration
22m
Detected by Pingoru
Jul 07, 2026, 08:27 PM UTC

Affected components

DINIT Processing Centre

Update timeline

  1. investigating Jul 07, 2026, 08:27 PM UTC

    We are currently experiencing an unplanned service outage in production that might affect you. Our technical teams are actively working to resolve the issue. Internal ticket MONET+ TSGCTCNAG-937043

  2. monitoring Jul 07, 2026, 08:49 PM UTC

    We are pleased to inform you that the system outage previously communicated has been resolved. We will monitor it.

  3. resolved Jul 07, 2026, 08:50 PM UTC

    We are pleased to confirm that the system outage was fully mitigated.

  4. postmortem Jul 07, 2026, 08:53 PM UTC

    Short-term unavailability caused by scheduled maintenance on the Monet+ side.