Switchio incident

Unplanned Outage of DINIT Processing Centre

Critical Resolved View vendor source →

Switchio experienced a critical incident on July 1, 2026 affecting DINIT Processing Centre, lasting 1h 38m. The incident has been resolved; the full update timeline is below.

Started
Jul 01, 2026, 06:37 AM UTC
Resolved
Jul 01, 2026, 08:16 AM UTC
Duration
1h 38m
Detected by Pingoru
Jul 01, 2026, 06:37 AM UTC

Affected components

DINIT Processing Centre

Update timeline

  1. investigating Jul 01, 2026, 06:37 AM UTC

    We are currently experiencing an unplanned service outage in production that might affect you. Our technical teams are actively working to resolve the issue. Internal ticket MONET+ TSGCTCNAG-933471

  2. monitoring Jul 01, 2026, 08:16 AM UTC

    We are pleased to inform you that the system outage previously communicated has been resolved. We will monitor it.

  3. resolved Jul 01, 2026, 08:16 AM UTC

    We are pleased to confirm that the system outage was fully mitigated.