Georgia Tech IT incident

PACE emergency cooling repair

Resolved after 13 days 22 hours, affecting Academic Services and Academic Services (PACE), on May 27, 2026.

monitoring May 27, 2026, 06:45 PM UTC

The repair was completed successfully, and job scheduling has resumed on all PACE clusters. No failure occurred, so running jobs were not disrupted. The datacenter team is monitoring the cooling system.

Started
May 27, 2026, 06:14 PM UTC
Resolved
Jun 10, 2026, 04:41 PM UTC
Duration
13d 22h
Detected by Pingoru
May 27, 2026, 06:14 PM UTC

Affected components

Academic ServicesAcademic Services (PACE)

Update timeline

  1. identified May 27, 2026, 06:14 PM UTC

    An emergency repair to the Coda datacenter cooling system began at 2 PM on Wednesday to avoid a reoccurrence of yesterday's failure (5/26). While no outage to PACE services is currently expected, PACE has paused scheduling new jobs on Phoenix, ICE, and Firebird in case of an unexpected cooling failure during the repair. New jobs will remain queued until the repair is complete. Visit https://status.gatech.edu for updates.

  2. monitoring May 27, 2026, 06:45 PM UTC

    The repair was completed successfully, and job scheduling has resumed on all PACE clusters. No failure occurred, so running jobs were not disrupted. The datacenter team is monitoring the cooling system.