Mechanical Disturbance - Equinix SY1

Minor Resolved View vendor source →

Servers Australia experienced a minor incident on March 19, 2025 affecting Equinix SY1 and Sydney and 1 more component, lasting 12h 23m. The incident has been resolved; the full update timeline is below.

Started
Mar 19, 2025, 08:43 AM UTC
Resolved
Mar 19, 2025, 09:06 PM UTC
Duration
12h 23m
Detected by Pingoru
Mar 19, 2025, 08:43 AM UTC

Affected components

Equinix SY1SydneyColocation

Update timeline

  1. investigating Mar 19, 2025, 08:43 AM UTC

    Equinix are investigating an issue with "SY1 - Mechanical - Cooling Zone" at the SY1 facility. We are awaiting further correspondence from them on this issue and will update this status accordingly.

  2. resolved Mar 19, 2025, 09:06 PM UTC

    Equinix IBX site staff reports that the System has been restored after a power outage. This issue is now resolved as of 19-March-2025 19:29 Site Local Time.