Sekoia FRA1 experienced a minor incident on March 20, 2026 affecting Automation, lasting 2d 23h. The incident has been resolved; the full update timeline is below.

Started
Mar 20, 2026, 08:25 AM UTC
Resolved
Mar 23, 2026, 08:13 AM UTC
Duration
2d 23h
Detected by Pingoru
Mar 20, 2026, 08:25 AM UTC

Affected components

Automation

Update timeline

  1. identified Mar 20, 2026, 08:25 AM UTC

    We are currently experiencing an incident affecting task execution due to a limitation in the cluster responsible for coordination and scheduling. This issue started yesterday around 18:26 and has prevented new processing tasks from starting. The engineering team has identified the root cause to mitigate the issue. Investigation and remediation efforts are ongoing.

  2. monitoring Mar 20, 2026, 09:05 AM UTC

    Pod scheduling and task execution have resumed following administrative actions on the cluster. The situation is currently being monitored.

  3. monitoring Mar 20, 2026, 03:56 PM UTC

    We are currently replaying the pending tasks and monitoring system stability.

  4. resolved Mar 23, 2026, 08:13 AM UTC