i3D.net incident

Backbone link down between Madrid - esmad1 & Paris - frpar1

Minor Ongoing

i3D.net is currently experiencing a minor incident affecting Datacenters (Madrid - esmad1) and Datacenters (Paris - frpar1), which began 2d ago. The vendor's full update timeline is below.

Started
Oct 19, 2026, 08:51 AM UTC
Resolved
Ongoing
Duration
● 1d 23h
Detected by Pingoru
Oct 19, 2026, 08:51 AM UTC

Affected components

Datacenters (Madrid - esmad1)Datacenters (Paris - frpar1)

Update timeline

  1. investigating Oct 19, 2026, 08:51 AM UTC

    We are currently experiencing some issues with our backbone link between Madrid - esmad1 and Paris - frpar1.

  2. identified Oct 19, 2026, 01:59 PM UTC

    We have identified the issue, we will continue to work towards a resolution.

  3. monitoring Oct 19, 2026, 01:59 PM UTC

    We have resolved the incident, we will keep monitoring the situation.