Funio incident

Critical issue with servers s111, s112, s113, and s114

Critical Resolved View vendor source →

Funio experienced a critical incident on March 8, 2026 affecting Shared Hosting, lasting 3h 3m. The incident has been resolved; the full update timeline is below.

Started
Mar 08, 2026, 11:14 PM UTC
Resolved
Mar 09, 2026, 02:17 AM UTC
Duration
3h 3m
Detected by Pingoru
Mar 08, 2026, 11:14 PM UTC

Affected components

Shared Hosting

Update timeline

  1. investigating Mar 08, 2026, 11:14 PM UTC

    We are currently investigating an issue with servers s111, s112, s113, and s114.

  2. investigating Mar 09, 2026, 01:04 AM UTC

    A system administrator is on his to the datacenter to investigate the issue. More details to come.

  3. investigating Mar 09, 2026, 01:57 AM UTC

    We have identified the issue and server's s112, s113 and s114 are all back up. We are still working on server s111. Thank you for your patience.

  4. resolved Mar 09, 2026, 02:17 AM UTC

    All servers are back up and running.