ThinkOn incident

Power Disturbance at KLP1 DC

Notice Resolved View vendor source →

ThinkOn experienced a notice incident on August 20, 2025 affecting KLP1 Internet Connectivity and KLP1 Virtual Compute, lasting 1h 28m. The incident has been resolved; the full update timeline is below.

Started
Aug 20, 2025, 03:33 PM UTC
Resolved
Aug 20, 2025, 05:01 PM UTC
Duration
1h 28m
Detected by Pingoru
Aug 20, 2025, 03:33 PM UTC

Affected components

KLP1 Internet ConnectivityKLP1 Virtual Compute

Update timeline

  1. investigating Aug 20, 2025, 03:33 PM UTC

    The DC team is currently investigating the power disturbance at the Data Centre.

  2. resolved Aug 20, 2025, 05:01 PM UTC

    We would like to inform you that the recent power disturbance at our Kamloops Data Centre has been fully resolved. All systems are now stable and operational.