ThinkOn experienced a notice incident on August 22, 2025 affecting CMB1 Internet Connectivity and CMB1 Virtual Compute and 1 more component, lasting 1d 1h. The incident has been resolved; the full update timeline is below.
Affected components
Update timeline
- investigating Aug 22, 2025, 07:01 PM UTC
We are currently investigating the issue.
- identified Aug 22, 2025, 07:17 PM UTC
We are currently working with a vendor to resolve the issue.
- identified Aug 22, 2025, 09:00 PM UTC
We continue working with a vendor to resolve the issue.
- identified Aug 22, 2025, 10:17 PM UTC
Our ThinkOn engineers are continuing to work with the vendor to resolve the issue.
- identified Aug 22, 2025, 10:35 PM UTC
Our vendor has dispatched field technicians to the site, and repair work is underway.
- identified Aug 23, 2025, 12:24 PM UTC
Fibre teams have successfully lashed the damaged fibers on both ends One cable has been fully spliced The fibres on the other end are currently being spliced
- monitoring Aug 23, 2025, 01:35 PM UTC
The fibre has been repaired and services have come back online. We are currently monitoring the network.
- resolved Aug 23, 2025, 08:20 PM UTC
This incident has been resolved.