Shock Hosting incident

NJ > NY Migration 1/2

Minor Resolved View vendor source →

Shock Hosting experienced a minor incident on April 22, 2024, lasting —. The incident has been resolved; the full update timeline is below.

Started
Apr 22, 2024, 01:30 PM UTC
Resolved
Apr 22, 2024, 01:30 PM UTC
Duration
Detected by Pingoru
Apr 22, 2024, 01:30 PM UTC

Update timeline

  1. resolved Apr 22, 2024, 01:30 PM UTC

    Type: Maintenance Duration: 6 hours and 50 minutes Affected Components: New York Apr 22, 13:30:01 GMT+0 - Identified - The 2-day process of migrating our equipment from New Jersey to New York has begun, the servers affected today are dedicated servers NJ-D33 thru NJ-D64 and the migration is expected to take approximately 6 hours to complete. Apr 22, 20:20:26 GMT+0 - Completed - NJ-D33 thru NJ-D64 have been migrated successfully. The next phase will start at 9 AM EST tomorrow.