Pulsant incident

Third party issue between at Rotherham YH-1

Major Resolved View vendor source →

Pulsant experienced a major incident on September 5, 2024 affecting YH1 - Sheffield, lasting 1d 5h. The incident has been resolved; the full update timeline is below.

Started
Sep 05, 2024, 09:49 AM UTC
Resolved
Sep 06, 2024, 03:01 PM UTC
Duration
1d 5h
Detected by Pingoru
Sep 05, 2024, 09:49 AM UTC

Affected components

YH1 - Sheffield

Update timeline

  1. identified Sep 05, 2024, 09:49 AM UTC

    Pulsant are aware of an issue at Rotherham YH-1. Third party engineers have investigated and identified the issue and Pulsant are currently awaiting an ETA for a fix. Currently Pulsant clients out of YH-1 are running at a lack of resiliency

  2. identified Sep 05, 2024, 12:21 PM UTC

    Third party engineers have made measurements and are now moving to the suspected damage location. Pulsant will update you as further information becomes available

  3. identified Sep 06, 2024, 08:06 AM UTC

    Pulsant's third Party have advised, engineers have identified the fault location leading to an inaccessible street cab . The team will be re-dispatched during normal business hours. Pulsant continue to monitor and chase for an ETA of a fix.

  4. monitoring Sep 06, 2024, 01:34 PM UTC

    Pulsants Third party have advised they have now resolved the issue and Pulsant have confirmed resiliency has been restored. Pulsant will continue to monitor services

  5. resolved Sep 06, 2024, 03:01 PM UTC

    Full resiliency has been restored to affected clients at YH-1. If you experience any further issues, please do not hesitate to contact Pulsant support.