Pulsant incident
LN-1 (Croydon) Data Centre - Pulsant Cloud Loss of resilience
Pulsant experienced a notice incident on January 8, 2025 affecting Pulsant Cloud LN-1 Croydon, lasting 22h 58m. The incident has been resolved; the full update timeline is below.
Affected components
Pulsant Cloud LN-1 Croydon
Update timeline
- investigating Jan 08, 2025, 10:13 AM UTC
Pulsant engineers have identified an possible upstream switch failure, resulting in loss of resilience. Investigations are ongoing to restore full resilience as quickly as possible.
- monitoring Jan 08, 2025, 12:02 PM UTC
Full resilience has been restored and being monitored closely. Pulsant engineers investigating to understand root cause.
- resolved Jan 09, 2025, 09:12 AM UTC
This incident has been resolved.