Celeste incident

Major outage on bus-ind datacenter

Notice Resolved View vendor source →

Celeste experienced a notice incident on February 26, 2026 affecting bus-ind, lasting 1d 2h. The incident has been resolved; the full update timeline is below.

Started
Feb 26, 2026, 11:00 AM UTC
Resolved
Feb 27, 2026, 01:23 PM UTC
Duration
1d 2h
Detected by Pingoru
Feb 26, 2026, 11:00 AM UTC

Affected components

bus-ind

Update timeline

  1. identified Feb 26, 2026, 04:28 PM UTC

    The issue has been identified and a fix is being implemented.

  2. identified Feb 26, 2026, 04:28 PM UTC

    We are continuing to work on a fix for this issue.

  3. monitoring Feb 26, 2026, 06:32 PM UTC

    A fix has been implemented and we are monitoring the results.

  4. resolved Feb 27, 2026, 01:23 PM UTC

    This incident has been resolved.