Simwood incident
Slough AZ – At-Risk Advisory (Power Maintenance)
Simwood experienced a notice incident on May 10, 2025 affecting Slough, lasting 22h 43m. The incident has been resolved; the full update timeline is below.
Affected components
Slough
Update timeline
- identified May 10, 2025, 08:00 AM UTC
The Slough Availability Zone is currently operating on a single power feed due to planned power infrastructure maintenance by our datacenter provider. While all services remain fully operational, the zone should be considered at risk until full power redundancy is restored. The maintenance window is scheduled to conclude by 22:59 UTC on Saturday, 10 May. We are closely monitoring the situation and will provide updates as needed.
- resolved May 11, 2025, 06:44 AM UTC
This incident has been resolved.