CyberLynk experienced a minor incident on March 26, 2025 affecting MKE1 Core Datacenter Infrastructure, lasting 27m. The incident has been resolved; the full update timeline is below.
Affected components
MKE1 Core Datacenter Infrastructure
Update timeline
- investigating Mar 26, 2025, 03:53 PM UTC
CyberLynk network engineers have identified an issue with one of our core switches in our MKE1 data center, which may cause latency/packet loss for some customers while traffic is rerouted.
- monitoring Mar 26, 2025, 04:01 PM UTC
Our network team identified an issue with a line card that has been resolved. We are continuing to monitor for any further issues.
- resolved Mar 26, 2025, 04:20 PM UTC
This incident has been resolved.