Data Pipeline Delay

Major Resolved View vendor source →

unitQ experienced a major incident on July 16, 2025 affecting unitQ Data Processing, lasting 3h 8m. The incident has been resolved; the full update timeline is below.

Started
Jul 16, 2025, 04:42 PM UTC
Resolved
Jul 16, 2025, 07:51 PM UTC
Duration
3h 8m
Detected by Pingoru
Jul 16, 2025, 04:42 PM UTC

Affected components

unitQ Data Processing

Update timeline

  1. investigating Jul 16, 2025, 04:42 PM UTC

    We are currently experiencing a delay processing data in our Data Pipeline and are investigating this issue.

  2. monitoring Jul 16, 2025, 04:55 PM UTC

    We have identified the cause of the delay. We are monitoring the data pipeline as it recovers.

  3. resolved Jul 16, 2025, 07:51 PM UTC

    We are currently processing data normally.