Tornado Datacenter incident

Increased cooling demand due to roof modernization

Major Resolved View vendor source →

Tornado Datacenter experienced a major incident on August 6, 2026 affecting Air Conditioning and Public Grid Power Supply, lasting 9d 6h. The incident has been resolved; the full update timeline is below.

Started
Aug 06, 2026, 11:32 AM UTC
Resolved
Aug 15, 2026, 05:37 PM UTC
Duration
9d 6h
Detected by Pingoru
Aug 06, 2026, 11:32 AM UTC

Affected components

Air ConditioningPublic Grid Power Supply

Update timeline

  1. monitoring Aug 06, 2026, 11:32 AM UTC

    TornadoDC is currently monitoring increased cooling demand caused by elevated solar heat gain. Due to the ongoing roof modernization above the datacenter, the roof insulation has been temporarily removed, resulting in a significantly higher thermal load on the facility and increased power consumption by the cooling infrastructure. As a precautionary measure, we have activated additional cooling capacity to maintain stable operating conditions. We have also ordered additional equipment to further strengthen the site's cooling capabilities during the remaining construction period. The measured temperature within the cold aisle remains well within our SLA-guaranteed limits, and there is no impact on customer services. The building owner and the construction contractor have been informed of the situation. We have received confirmation that the affected roof section above the datacenter has been prioritized and that work on this area will be completed as quickly as possible. We will continue to closely monitor the situation and provide further updates if necessary.

  2. monitoring Aug 10, 2026, 07:07 AM UTC

    We got informed by the building owner, the contractor responsible for the roof modernization will start the works as of today in order to restore outer insulation above the datacenter.

  3. monitoring Aug 11, 2026, 09:38 AM UTC

    In coordination with the manufacturer of the chilled-water system, we have implemented several optimizations to maintain more stable temperatures while reducing capacity fluctuations. Temporary roof insulation has also been installed to minimize additional heat gain. Additional cooling equipment is scheduled for delivery tomorrow, providing increased thermal capacity and additional headroom for the remainder of the 2026 summer season. This will allow the existing DX air-conditioning units to remain reserved for emergency and exceptional operating conditions, such as the current situation, rather than being required during normal operation. In summer 2027, the existing DX air-conditioning units will be replaced with in-row CRAH units, further increasing cooling capacity and improving overall efficiency and temperature stability.

  4. resolved Aug 15, 2026, 05:37 PM UTC

    We're closing the same, cold aisle temperatures were stable over the past days and behaved as planned.