Targetprocess incident

Intermittent Performance Degradation for Dublin Data Centers(poveu cluster)

Minor Resolved View vendor source →

Targetprocess experienced a minor incident on January 22, 2025 affecting POVEU cluster, lasting 3h 18m. The incident has been resolved; the full update timeline is below.

Started
Jan 22, 2025, 03:41 AM UTC
Resolved
Jan 22, 2025, 07:00 AM UTC
Duration
3h 18m
Detected by Pingoru
Jan 22, 2025, 03:41 AM UTC

Affected components

POVEU cluster

Update timeline

  1. investigating Jan 22, 2025, 07:41 AM UTC

    We are currently investigating this issue.

  2. resolved Jan 22, 2025, 11:09 AM UTC

    This incident has been resolved.