SashiDo experienced a minor incident on December 9, 2021 affecting API and Redirector and 1 more component, lasting 5d 18h. The incident has been resolved; the full update timeline is below.
Affected components
Update timeline
- scheduled Dec 09, 2021, 03:19 PM UTC
Our Datacenter provider is planning to do a internal network upgrade where our servers are located. Small outages are expected during the maintenance period. The outage should be approximately 10 minutes per server. The maintenance will be splitted in 3 batches, we invite you to check the following status page of our datacenter for further information : https://status.scaleway.com/incidents/p4c5d2r2r3zj
- scheduled Dec 15, 2021, 06:00 AM UTC
Maintenance will begin as scheduled in 60 minutes.
- scheduled Dec 15, 2021, 06:35 AM UTC
We will be undergoing scheduled maintenance during this time.
- in progress Dec 15, 2021, 06:36 AM UTC
Scheduled maintenance is currently in progress. We will provide updates as necessary.
- completed Dec 15, 2021, 10:00 AM UTC
The scheduled maintenance has been completed.