FUSION 1 experienced a minor incident on April 21, 2026 affecting Ashburn, VA-US (IAD) Data Center, lasting 22h 25m. The incident has been resolved; the full update timeline is below.
Affected components
Update timeline
- identified Apr 21, 2026, 11:40 PM UTC
April 21, 2026 20:49 UTC IDENTIFIED The rack containing the affected hosts is not stable. Many of the affected resources are up, but some remain inaccessible or unstable. We are working to move resources from this rack to new hosts. April 21, 2026 18:07 UTC IDENTIFIED All affected resources are currently up, but the datacenter team is still working to ensure the stability of each host. April 21, 2026 16:49 UTC IDENTIFIED Most impacted resources are recovering and the datacenter team is troubleshooting the remaining affected hosts. April 21, 2026 15:08 UTC IDENTIFIED We have identified the issue and the datacenter team is working on stabilizing the affected resources. April 21, 2026 14:30 UTC INVESTIGATING We are aware of an issue affecting a PCI host in this region. Some PCI instances may be unavailable or unresponsive during this time. Our teams are actively working toward a resolution, and updates will be shared as progress is made. We apologize for the inconvenience.
- resolved Apr 22, 2026, 10:06 PM UTC
This incident has been resolved.