Deft experienced a notice incident on September 6, 2018, lasting 53m. The incident has been resolved; the full update timeline is below.
Update timeline
- investigating Sep 06, 2018, 04:28 PM UTC
We are investigating reports of an issue relating to issues connecting to the Veeam Cloud Connect repository in our Elk Grove Village area datacenter.
- identified Sep 06, 2018, 04:34 PM UTC
We have identified the issue and are working to restore service.
- identified Sep 06, 2018, 04:40 PM UTC
Services have been restored and are resuming normal activity. We are continuing to monitor the platform to ensure stability.
- resolved Sep 06, 2018, 05:22 PM UTC
This issue has been deemed resolved by our Managed Services team and all functionality is operating normally.