AppVeyor incident

Emergency power maintenance in macOS data center

Maintenance Resolved View vendor source →

AppVeyor performed scheduled maintenance on November 9, 2024, lasting 6d 16h. The full update timeline is below.

Started
Nov 09, 2024, 09:28 PM UTC
Resolved
Nov 16, 2024, 02:00 PM UTC
Duration
6d 16h
Detected by Pingoru
Nov 09, 2024, 09:28 PM UTC

Update timeline

  1. scheduled Nov 09, 2024, 09:28 PM UTC

    There is going to be a maintenance in the data center hosting macOS workers. Cloud capacity will be reduced during that time.

  2. scheduled Nov 16, 2024, 01:00 AM UTC

    Maintenance will begin as scheduled in 60 minutes.

  3. investigating Nov 16, 2024, 02:00 AM UTC

    Scheduled maintenance is currently in progress. We will provide updates as necessary.

  4. resolved Nov 16, 2024, 02:00 PM UTC

    completed — The scheduled maintenance has been completed. (2024-11-16T06:00:21.155-08:00) in_progress — Scheduled maintenance is currently in progress. We will provide updates as necessary. (2024-11-15T18:00:21.310-08:00) scheduled — Maintenance will begin as scheduled in 60 minutes. (2024-11-15T17:00:30.968-08:00) scheduled — There is going to be a maintenance in the data center hosting macOS workers. Cloud capacity will be reduced during that time. (2024-11-09T13:28:53.815-08:00)

  5. completed Nov 16, 2024, 02:00 PM UTC

    The scheduled maintenance has been completed.